You can study over 10 years of 1st grade civil engineering construction management engineer department past questions repeatedly on your mobile phone or tablet. This is an app for people who aim to pass exams while commuting, studying on their own, and reviewing past exam questions.

Features & Capabilities

For the 2026 exam.

Includes questions from the 2025 (First Stage) to 2011 (Heisei 23) exams.

No in-app purchases or ads.

Each question is presented with a clear [Question ⇒ Answer] link for quick and easy review.

The answer page also includes the original question, making reviewing easier.

The "Learning Confirmation Test" (R7-H28), featuring randomly generated questions (10/multiple questions), allows you to check your understanding.

You can also focus on studying multiple-choice questions from the 2022 (First Stage) to 2011 (Morning) exams (No. 1-15).

Study little by little during your commute on trains and buses, or during breaks.

*This includes past exam questions from 2025 (First Stage), 2024 (First Stage), 2023 (First Stage), 2021 (First Stage), 2020 (First Stage), 2020 (First Stage), 2020 (First Stage), 2019 (First Stage), 2018 (First Stage), 2017 (First Stage), 2016 (First Stage), 2015 (First Stage), 2014 (First Stage), 2013 (First Stage), 2012 (First Stage), and 2011 (First Stage).

This is suitable for reviewing past exam questions.

One of the most important things for obtaining a qualification is reviewing past exam questions.

By reviewing past exam questions, you can understand the structure of the questions, the types of questions that tend to appear, and your own strengths and weaknesses. Therefore, you can use past exam questions to create an exam preparation and study plan, such as which areas to focus on and which areas to score points in.

Understand the trends in the questions, find your own study method, and proceed with your studies systematically.

[Example Problems]
Reiwa 6 (2024) Problem A [No. 7]
Which of the following statements regarding points to note when using excavated soil as road embankment material is incorrect?
Materials that pose problems for embankment stability or settlement should be spread as thickly as possible in the lower layer of the embankment, or used on the slope crest, etc.

Reiwa 6 (2024) Problem A [No. 8]
Which of the following statements regarding information-based construction of embankments using TS (Total Station) and GNSS (Global Navigation Satellite System) is incorrect?
When compacting embankment material, compaction should be carried out until the representative point set within the embankment area, as shown on the compaction count distribution map displayed on the in-vehicle computer monitor, changes color to indicate that the specified number of compactions have been achieved, ensuring that the number of compactions determined in the test construction is secured.

Reiwa 6 (2024) Problem A [No. 9]
Which of the following statements regarding points to note when using excavated soil for backfilling structures is incorrect?

The soil used for backfilling should be highly compressible to prevent gaps or unevenness between the structure and the backfill after the road is opened to traffic.

Reiwa 6 (2024) Exam A [No. 10]
Which of the following descriptions regarding soft ground improvement methods is incorrect?
The high-pressure injection grouting method forcibly mixes the soft soil in situ with a solidifying agent using grouting blades to form stabilized soil and increase sliding resistance.

Reiwa 6 (2024) Exam A [No. 11]
Which of the following descriptions regarding coarse aggregate for concrete is incorrect?
When crushed stone is used, the unit water content needs to be smaller compared to when gravel is used in order to obtain concrete with good workability.

Reiwa 6 (2024) Exam A [No. 12]
Which of the following descriptions regarding testing methods for concrete aggregate is incorrect?
The suitability of aggregate quality against repeated freeze-thaw cycles is determined by the abrasion test of coarse aggregate using the Los Angeles Test Machine.
Reiwa 6 (2024) Fiscal Year, Problem A [No. 13]
Which of the following statements regarding concrete mix design is correct?
When setting the slump considering the compaction height, the slump value should be set higher for the compaction height of 2m compared to 0.5m.
Reiwa 6 (2024) Fiscal Year, Problem A [No. 14]
Which of the following statements regarding the construction of cold-weather and hot-weather concrete is incorrect?
When the minimum daily temperature is expected to be 4°C or lower during concrete construction, the construction must be carried out as cold-weather concrete.
Reiwa 6 (2024) Fiscal Year, Problem A [No. 15]
Which of the following statements regarding concrete curing is incorrect?
The wet curing period for concrete using mixed cement type B is shorter than that for concrete using ordinary Portland cement.
Reiwa 6 (2024) Fiscal Year, Problem A [No. 16]
When construction conditions are the same, which of the following statements regarding the lateral pressure of fresh concrete acting on formwork is incorrect?

The higher the concrete temperature, the greater the lateral pressure.

Reiwa 6 (2024) Exam A [No. 17]
Which of the following descriptions regarding various foundation types in road bridge substructures is incorrect?
In direct foundations, since the shear surface when the foundation slides occurs at a deep point on the foundation's base, it is fundamental to avoid causing excessive disturbance to the ground during construction.

Reiwa 6 (2024) Exam A [No. 18]
Which of the following descriptions regarding the construction of steel pipe pile foundations using the driven pile method is correct?
For supporting pile foundations, the stopping of driving should be confirmed to be similar to that of test piles based on the embedment depth, rebound amount per drive at the time of stopping, etc.

Reiwa 6 (2024) Exam A [No. 19]
Which of the following descriptions regarding construction using the cast-in-place pile method is incorrect?
In the all-casing method, the concrete top surface does not sink by pulling out the casing tube after concrete pouring is complete.

Reiwa 6 (2024) Exam, Problem A [No. 20]
Which of the following descriptions regarding the characteristics of various earth retaining structures is incorrect?
Self-supporting earth retaining is a method that resists through the rigidity of the earth retaining wall, resulting in small deformation of the earth retaining wall and easy excavation because there is no shoring within the excavation surface.
Reiwa 6 (2024) Exam, Problem A [No. 21]
Which of the following descriptions regarding precautions for erecting steel road bridges is incorrect?
When moving erection members in the longitudinal direction, it is desirable to make the launching slope a downward slope to improve the safety of the launching operation.
Reiwa 6 (2024) Exam, Problem A [No. 22]
Which of the following descriptions regarding precautions for welding work on steel road bridges is incorrect?
Undercuts are a major cause of stress concentration and lead to accelerated corrosion, so they should not be present even in joints that are not considered to be affected by fatigue.
Reiwa 6 (2024) Exam, Problem A [No. 23]
Which of the following descriptions regarding tightening work of high-strength bolts on steel road bridges is correct?

High-strength bolts should be tightened sequentially from the central bolt of the connecting plate to the end bolts, and tightened twice.

Reiwa 6 (2024) Problem A [No. 24]
Which of the following statements regarding reinforcement methods for concrete structures is incorrect?
Seismic isolation methods can reduce the displacement of members during earthquakes.

Reiwa 6 (2024) Problem A [No. 25]
Which of the following statements regarding deterioration due to carbonation of concrete structures and its characteristics is incorrect?
The carbonation depth of concrete can generally be considered to be proportional to the square of the number of years of service after the completion of the structure.

Reiwa 6 (2024) Problem A [No. 26]
Which of the following statements regarding embankment construction for river levees is correct?
In embankment construction, temporary drainage channels are provided at appropriate intervals to allow rainwater to flow down in order to prevent slope erosion due to rainfall, and a drainage gradient is provided in the direction transverse to the embankment to prevent the concentration of rainwater.
Reiwa 6 (2024) Examination Question A [No. 27]
Which of the following statements regarding foundation protection work installed on the front of river revetments is incorrect?
The construction of irregularly shaped concrete blocks involves leveling the riverbed before stacking, so construction becomes difficult as the water depth increases.
Reiwa 6 (2024) Examination Question A [No. 28]
Which of the following statements regarding open-cut construction of river embankments is incorrect?
When constructing sluice gates and culverts, it is desirable to make the excavation of the existing embankment large so that the attachment embankment can be easily constructed, and the same applies from the perspective of river management.
Reiwa 6 (2024) Examination Question A [No. 29]
Which of the following statements regarding the construction of sediment control dams is incorrect?
In sediment control dams, backfilling is generally done in the excavated section, and if the foundation excavation section is bedrock, backfilling is done with sand and gravel.
Reiwa 6 (2024) Examination Question A [No. 30]
Which of the following statements regarding landslide prevention work is correct?

Anchor construction is a method of stabilizing a slope by inserting tendons (steel materials, etc.) into the stable ground from the slope and utilizing the tensile strength of the steel materials fixed within the base. There are two types: one that utilizes a tightening effect and another that utilizes a restraining effect.

Reiwa 6 (2024) Problem A [No. 31]
Which of the following statements regarding steep slope collapse prevention construction is incorrect?
Cast-in-place concrete frame construction is used when a stable gradient cannot be obtained on the cut slope, etc., and the girder structure generally uses unreinforced concrete.

Reiwa 6 (2024) Problem A [No. 32]
Which of the following statements regarding the construction of the subgrade in asphalt road pavement is correct?
The embankment subgrade should be uniformly laid after thoroughly understanding the properties of the embankment material used, and finished by sufficiently compacting to prevent strength reduction due to over-compaction.

Reiwa 6 (2024) Problem A [No. 33]
Which of the following statements regarding the construction of the upper subgrade in asphalt road pavement is incorrect?

When constructing a heated asphalt stabilized roadbed using the thick-lift method, if there is no restraint at the lateral edges, it is advisable to compact it with a large compaction machine such as a vibratory roller.

*While every effort has been made to ensure the accuracy of points and other information within the app, please note that accuracy cannot be guaranteed.

We assume no responsibility whatsoever for any inconvenience or disadvantage resulting from the use of this app.

*The content within the app may be added, updated, changed, or modified without prior notice.

User Growth & Download Statistics

Contact the developer

Chrome-Stats does not own this Android app. Please use these information below to contact the Android app developer.
Developed by:
ソイルプランニング
Google Play Store
https://play.google.com/store/apps/details?id=com.dob1sekokan
Email:
so*****@gmail.com

Best 1級土木施工管理学科過去問題/令和7年1次~平成23年 Alternatives

Here are some Android apps that are similar to 1級土木施工管理学科過去問題/令和7年1次~平成23年: